DIFFERENT FUEL OPTIONS FOR THE 15-MONTH CYCLES OF PAKS NPP UNITS
24th Symposium of AER on VVER Reactor Physics and Reactor Safety (2014, Sochi, Russia)
Fuel management issues
Abstract
DIFFERENT FUEL OPTIONS FOR THE 15-MONTH CYCLES OF PAKS NPP UNITS
Imre Nemes, István Pós, Paks NPP Ltd, Sándor Patai Szabó , TS Enercon Ltd., Hungary
ABSTRACT
4 Units of Paks NPP are planned to operate in 15 month cycles. The number of fresh fuel planned for this cycles is 102/unit/cycle. In this work we tried to improve fuel demand of 15m cycles, the goal was to establish 90 assembly/cycle strategies. For this purpose different developed assembly structure was investigated. Appropriate enrichment is determined, CCS libraries was generated to different versions and equilibrium cycles are arranged. Fresh fuel cost and benefits are calculated for each version.